Subwatershed Stormwater Retrofit Assessment
Today, regulations require stormwater treatment before discharge to lakes, rivers, and streams. However, areas developed before these requirements may lack adequate treatment. We focus on retrofitting stormwater practices into these existing landscapes, identifying and prioritizing projects based on water quality benefits per dollar spent. This approach positions us to secure grant funding and collaborate with partners to implement the most cost-effective projects.
In response to these issues, ACD staff conduct subwatershed stormwater retrofit assessments to identify retrofit opportunities in subwatersheds that are significant contributors to the degradation of high-priority water bodies.
Today, regulations require treatment of stormwater before it is discharge to lakes, rivers, and streams. But areas built before these regulations may have inadequate treatment. There, we focus on retrofitting new practices into the landscape. We identify and rank potential projects based on benefit per dollar spent. Then, we are well-positioned to secure grants and work with partners to install the best projects.
Stormwater Retrofit Process
Step 1: Assessment Scoping
Refine the retrofit strategy to meet local restoration objectives
- Define core retrofitting objectives. Identify preferred retrofit treatment options.
- Delineate the subwatershed focus area.
Step 2: Desktop Analysis
Search for potential retrofit sites throughout the subwatershed; secure GIS and other mapping.
- Conduct a desktop search for potential retrofit sites.
- Prepare base maps for field reconnaissance.
Step 3: Subwatershed Reconnaissance
Investigate retrofit sites in the field
- Verify drainage areas and mapping data. Assess site constraints
- Search for additional retrofit opportunities
Step 4: Treatment Analysis/Cost Estimates
Create project concepts and model for treatment potential
- Develop project concepts and cost estimates
- Model for volume and pollutant reduction
Step 5: Evaluation and Ranking
Compare projects throughout the subwatershed
- Conduct cost/benefit analysis for project concepts
- Rank projects by cost-effectiveness
- Compare results to restoration objectives
Step 6: Reporting
Create a detailed report of assessment findings and recommended projects
- Deliver final report to project partners
- Conduct one verbal presentation of assessment findings to project partners

Our Projects
Since 2009, ACD staff have completed nearly 30 subwatershed stormwater retrofit assessments. Targeted high-priority water bodies have included creeks, rivers, and lakes.
See the links below for reports. Installed projects can be viewed in our Projects Dashboard.
Subwatershed Stormwater Retrofit Analysis Reports
2025 Trott Brook Water Quality Restoration Assessment
2024 Rum River, Anoka, Ramsey, and Andover
2024 Mississippi River, Anoka and Coon Rapids
2024 Ford Brook, Pickerel and East Twin Lake
2023 Centerville Lake Centerville & Lino Lakes
2021 Lower Rice Creek, Fridley and Spring Lake Park
2019 Highland and Sullivan Lakes, Columbia Heights and Fridley
2018 Ditch 20 Wetland Restoration Feasibility Study, Isanti & Anoka County
2018 Lake George Lakeshed Analysis, Oak Grove and St. Francis
2018, Ditch 20 Wetland Restoration Feasibility Study, Linwood Township and Isanti County
2016 Rum River/Mississippi, Ramsey
2016 Pleasure Creek, Blaine and Coon Rapids
2014 Stonybrook, Fridley and Spring Lake Park
2014 Skogman-Fannie-Elms-Florence Lakes Chain, Cambridge and Fish Lake Township
2014 Lake Sarah & Lake Independence, City of Independence
2014 Coon Lake, East Bethel, Ham Lake, Columbus & Linwood Township
2014 Southern Columbia Heights & Northeast Minneapolis
2012 Lower Coon Creek, Coon Rapids 2011 City of Isanti
2011 Golden Lake, Blaine, Circle Pines & Lexington
2011 Martin Lake, Lindwood Township
2010 Woodcrest Creek, Blaine & Coon Rapids