Subwatershed Stormwater Retrofit Assessment

Today, regulations require stormwater treatment before discharge to lakes, rivers, and streams. However, areas developed before these requirements may lack adequate treatment. We focus on retrofitting stormwater practices into these existing landscapes, identifying and prioritizing projects based on water quality benefits per dollar spent. This approach positions us to secure grant funding and collaborate with partners to implement the most cost-effective projects.

In response to these issues, ACD staff conduct subwatershed stormwater retrofit assessments to identify retrofit opportunities in subwatersheds that are significant contributors to the degradation of high-priority water bodies.

Today, regulations require treatment of stormwater before it is discharge to lakes, rivers, and streams. But areas built before these regulations may have inadequate treatment. There, we focus on retrofitting new practices into the landscape. We identify and rank potential projects based on benefit per dollar spent. Then, we are well-positioned to secure grants and work with partners to install the best projects.

Stormwater Retrofit Process

Step 1: Assessment Scoping

Refine the retrofit strategy to meet local restoration objectives

  • Define core retrofitting objectives. Identify preferred retrofit treatment options.
  • Delineate the subwatershed focus area.
Step 2: Desktop Analysis

Search for potential retrofit sites throughout the subwatershed; secure GIS and other mapping.

  • Conduct a desktop search for potential retrofit sites.
  • Prepare base maps for field reconnaissance.
Step 3: Subwatershed Reconnaissance

Investigate retrofit sites in the field

  • Verify drainage areas and mapping data. Assess site constraints
  • Search for additional retrofit opportunities
Step 4: Treatment Analysis/Cost Estimates

Create project concepts and model for treatment potential

  • Develop project concepts and cost estimates
  • Model for volume and pollutant reduction
Step 5: Evaluation and Ranking

Compare projects throughout the subwatershed

  • Conduct cost/benefit analysis for project concepts
  • Rank projects by cost-effectiveness
  • Compare results to restoration objectives
Step 6: Reporting

Create a detailed report of assessment findings and recommended projects

  • Deliver final report to project partners
  • Conduct one verbal presentation of assessment findings to project partners
ACD Specialist for Stormwater Retrofit:
Mitch Haustein ~ 763-434-2030 x150
Stormwater Map

Our Projects

Since 2009, ACD staff have completed nearly 30 subwatershed stormwater retrofit assessments. Targeted high-priority water bodies have included creeks, rivers, and lakes.

See the links below for reports. Installed projects can be viewed in our Projects Dashboard.